Rankers Hub

Time and Work Problems

MCQ on Time and Work

Answer the following Time and Work Problems:

4 women and 12 children together take four days to complete a piece of work. How many days will four children alone take to complete the piece of work if two women alone can complete the piece of work in 16 days?

(a) 32

(b) 24

(c) 16

(d) 12

(e) None of these

Solution: (b)

Two women alone can complete a piece of work in 16 days.

Therefore, Four women can complete the same work in 8 days.

12 children can complete the work in = \(\displaystyle \frac{{4\times 8}}{{8-4}}=\frac{{4\times 8}}{4}=8days\)

Four children can complete the work in = \(\displaystyle \frac{{12\times 8}}{4}=24days\)

9 women can complete a piece of work in 19 days. How many days will 18 women take to complete the same piece of work?

(a) 12 days

(b) 6.5 days

(c) 9 days

(d) 8.5 days

(e) None of these

Solution: (e)

\(\displaystyle {{M}_{1}}{{D}_{1}}={{M}_{2}}{{D}_{2}}\)

\(\displaystyle \Rightarrow \)

\(\displaystyle \Rightarrow \) \(\displaystyle 9\times 19=18\times {{D}_{2}}\)

\(\displaystyle \Rightarrow \) \(\displaystyle {{D}_{2}}\) = \(\displaystyle \frac{{9\times 19}}{{18}}=9.5days\)

12 men alone can complete a piece of work in 6 days. Whereas 10 men and 21 women together take 3 days to complete the same piece of work.  In how many days can 12 women alone complete the piece of work?

(a) 10

(b) 9

(c) 11

(d) 8

(e) None of these

Solution: (b)

12 men complete the work in 6 days.

Therefore, 1 man’s 1 day’s work = \(\displaystyle \frac{1}{{72}}\)

Therefore, 10 men’s 3 day’s work = \(\displaystyle \frac{{10\times 3}}{{72}}=\frac{5}{{12}}work\)

Remaining work = \(\displaystyle 1-\frac{5}{{12}}=\frac{7}{{12}}\)

Therefore, 21 women do \(\displaystyle \frac{7}{{12}}\) work in 3 days.

Therefore, By \(\displaystyle \frac{{{{M}_{1}}{{D}_{1}}}}{{{{W}_{1}}}}=\frac{{{{M}_{2}}{{D}_{2}}}}{{{{W}_{2}}}}\)

\(\displaystyle \frac{{21\times 3}}{{\frac{7}{{12}}}}=\frac{{12\times {{D}_{1}}}}{1}\Rightarrow \frac{{21\times 3\times 12}}{{7\times 12}}={{D}_{2}}\)

\(\displaystyle {{D}_{2}}=9days\)

A and B together can complete a particular task in 8 days. If B alone can complete the same task in 10 days, how many days will A take to complete the task if he works alone ?

(a) 28

(b) 36

(c) 40

(d) 32

(e) None of these

Solution: (c)

Let the A can do the task in x days

\(\displaystyle \frac{1}{x}+\frac{1}{{10}}=\frac{1}{8}\)

\(\displaystyle \frac{1}{x}=\frac{1}{8}-\frac{1}{{10}}=\frac{{10-8}}{{80}}=\frac{2}{{80}}=\frac{1}{{40}}\) 

 X = 40

Alternate Method

If total work = 80 units

Then in 1 day (A+B) will do 80/10 = 10 unit of work

Therefore, A does 2 unit of work each day

Hence, A requires 80/2 = 40 days to complete work

A alone can make 100 baskets in 6 days and B alone can make 100 baskets in 12 days. In how many days can A and B together make 100 baskets?

(a) 3 days

(b) 5 days

(c) \(\displaystyle 2\frac{1}{2}days\)

(d) \(\displaystyle 3\frac{1}{2}days\)

(e) None of these

Solution: (e)

A’s 1 day’s work = \(\displaystyle \frac{1}{6}\)\(\displaystyle \frac{1}{6}\)

B’s 1 day’s work = \(\displaystyle \frac{1}{{12}}\)

Therefore, (A + B)’s 1 day’s work = \(\displaystyle \frac{1}{6}+\frac{1}{{12}}=\frac{{2+1}}{{12}}=\frac{1}{4}\)

Hence, A and B together will make 100 baskets in 4 days.

Alternate method

A alone can make 100 baskets in 6 days and B alone can make in 12 days.

Therefore, Rate of efficiency of A=100/6 baskets per day

And rate of efficiency of B=100/12 baskets per day

⇒ Baskets made by A and B together in 1 day = \(\displaystyle \frac{{100}}{6}+\frac{{100}}{{12}}=\frac{{300}}{{12}}=25\)= baskets per day

Therefore, Time taken by A and B together to make 100 baskets= \(\displaystyle \frac{{100}}{{25}}\)=4 days

8 men and 4 women together can complete a piece of work in 6 days. The work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days 4 men left and 4 new women joined, in how many more days will the work be completed?

(a) 5 days

(b) 8 days

(c) 6 days

(d) 4 days

(e) 9 days

Solution: (a)

1M = 2W

(8M + 4W) × (6 days – 2 days) = (4M + 8W) × x days

(8 × 2W + 4W) × (6 – 2) days = (4 × 2W + 8W) × x days

(16 + 4)W × 4 days = 16W × x days

X = \(\displaystyle \frac{{20\times 4}}{{16}}=5days[{{M}_{1}}{{D}_{1}}={{M}_{2}}{{D}_{2}}]\)

Pipes A and B can fill a tank in 5 and 6 hours, respectively. Pipe C can empty it in 12 hours. The tank is half full. All the three pipes are in operation simultaneously. After how much time, the tank will be full ?

(a) \(\displaystyle 3\frac{9}{{17}}h\)

(b) 11 h

(c) \(\displaystyle 2\frac{8}{{11}}h\)

(d) \(\displaystyle 1\frac{{13}}{{17}}h\)

(e) None of these

Answer for this Time and Work Problem is (d)

Part of the tank filled by the three pipes working simultaneously in one hour is

= \(\displaystyle \frac{1}{5}+\frac{1}{6}-\frac{1}{{12}}=\frac{{17}}{{60}}\)

i.e. it takes \(\displaystyle \frac{{60}}{{17}}\) hours to fill up the tank completely.

Now,  of the tank is filled with all the pipes open, simultaneously together in

\(\displaystyle \frac{{60}}{{17}}\times \frac{1}{2}=1\frac{{13}}{{17}}hours\)

A and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is

(a) 12

(b) 9

(c) 15

(d) 10

(e) None of these

Answer for this Time and Work Problem is (b)

A and B can complete work in 6 days

A can complete in 18 days

Let B can complete in x days

\ One day work be equal to \(\displaystyle \frac{1}{6}=\frac{1}{{18}}+\frac{1}{x}\)

\(\displaystyle \frac{1}{6}=\frac{{x+18}}{{18x}}\)

3x = x + 18

x = 9 days